Deadline planner
Put in a real donor deadline and a tier. The schedule is derived backwards over the Uganda working calendar — weekends and public holidays removed — so what you get is the day the cycle has to start, and how many working days of slack are left if it does not. Nothing here is saved.
Where does the deadline put us?
Enter the donor’s date. Every other date is derived backwards from it over a working-day calendar that knows Uganda’s public holidays — nobody types a stage date, they receive one.
This bid does not fit — it is 20 working days shortFloat -20 working daysWork must start 2026-09-11Cycle needs 35 working days
The derived plan
| Stage | Segment | Start | End | Days | Accountable | Gate |
|---|---|---|---|---|---|---|
| 2 | Qualify · Go/No-Go | 2026-09-11 | 2026-09-14 | 2 | PPL | G1 |
| 3 | Co-design with partner | 2026-09-15 | 2026-09-28 | 10 | TL | G2 |
| 4 | Drafting · proposal and budget | 2026-09-29 | 2026-10-13 | 10 | TL | |
| 4 | Technical review · TL + DER reserved | 2026-10-14 | 2026-10-16 | 3 | DER | |
| 4 | Business review · PPL + DOI + BFL reserved | 2026-10-19 | 2026-10-21 | 3 | DOI | |
| 4 | Donor compliance check and QA checklist | 2026-10-22 | 2026-10-23 | 2 | GRANTS | |
| 4 | Design approval reserved | 2026-10-26 | 2026-10-27 | 2 | CD | G3 |
| 5 | Final clearance, packaging and submission | 2026-10-28 | 2026-10-30 | 3 | PPL | G4 |
Gate decisions and who signs them
| Gate | Decision due by | Required signatures |
|---|---|---|
| Gate 1 · Pursue? | 2026-09-14 | PPL + CD |
| Gate 2 · Concept | 2026-09-28 | PPL |
| Gate 3 · Design approval | 2026-10-27 | PPL + CD |
| Gate 4 · Submit | 2026-10-30 | CD |